Connect with us

News

Ongoing repairs at Pyramid substation nearly done

Published

on

Tshwane Metro Makes Progress in Repairing Pyramid Substation

The Tshwane metro reported significant progress in the repair of the Pyramid substation following a fire that caused widespread frustration among residents.

Repair Work Update
– The repair work on the substation is over 80% complete.
– Technicians have completed repairs to the damaged multi-core cables and conducted pressure testing on medium voltage equipment.
– Remaining tasks include finalizing cabling work, purifying transformer oil, and reconnecting busbars.
– Estimated time for full restoration is still pending.

Impact on Residents
– The fire left many residents in Rooiwal without electricity for several days.
– Outages extended to areas like Pretoria North, Wonderboom, Wolmer, and parts of Waltloo.
– Previous fires at the Pyramid substation in 2019 and 2022 have raised concerns about infrastructure reliability.

Residents’ Concerns
– Residents express dissatisfaction with prolonged outages and lack of transparency from metro officials.
– Allegations of sabotage have surfaced, prompting calls for a thorough investigation.
– Economic consequences of outages are felt by local businesses and the metro’s revenue.

Future Outlook
– Community members demand transparency and a commitment to improving energy supply reliability.
– Calls for the metro to address underlying issues at the substation to prevent future disruptions.

Advertisement

For further information or tips on the story, please contact [email protected] or call 083 625 4114.

Stay updated on breaking news on Rekord East’s website and follow Rekord on social media platforms for more news updates.

Source: The Citizen

Continue Reading
Advertisement